BC Hydro Bets on Interest Rates — and Loses $1 Billion

A hedging program was supposed to protect the corporation from rising rates. Instead, it’s creating major liabilities.

Andrew Nikiforuk 7 Oct 2020TheTyee.ca

Andrew Nikiforuk is an award-winning journalist who has been writing about the energy industry for two decades and is a contributing editor to The Tyee. Find his previous stories here.

Critics are calling it another BC Hydro scandal. The Crown corporation, already beset by burgeoning costs and geotechnical difficulties at the controversial Site C dam, has racked up $1 billion of liabilities betting on interest rates.

BC Hydro revealed the losses in its first-quarter report, released in September.*

Marc Eliesen, former CEO of BC Hydro and Ontario Hydro, said the corporation’s gamble that it could predict future interest rates has backfired. “BC Hydro took a trip to the casino and played roulette and lost big time,” he said.

The interest rate hedging program began in 2016 with the goal of protecting ratepayers from higher future borrowing costs if rates rose.

Under the program, BC Hydro bought investment vehicles that would increase in value if interest rates rose. The corporation’s managers believed the profits could be used to offset higher borrowing costs if, as they predicted, interest rates went up.

“They thought they would make money on interest rate hedges and put it in a default account which would help offset borrowing costs in the future,” explained Richard McCandless, a former civil servant who wrote about the loss on his blog.

Instead, interest rates fell, and BC Hydro has lost money on the hedging program.

“It is a scandal,” said McCandless. “They took a gamble and lost.”

BC Hydro, which carries $23.3 billion in debt, anticipates the need to borrow another $10 billion between 2017 and 2024, partly to pay for the over-budget Site C dam and about $2 billion a year in other capital projects.

The hedging program gained approximately $160 million by fiscal 2017/18.

But as interest rates declined, losses began to increase sharply beginning in 2018. They have now ballooned to more than $1 billion.

“Will they continue to lose money?” asked Eliesen. “Yes, because all the monetary authorities say interest rates will be low or lower in the future due to the pandemic.

“We now have $1 billion in liabilities that will be passed onto Hydro ratepayers — the citizens who consume and pay for electricity in the province,” he said. “This is another black mark on BC Hydro, and no one has taken responsibility.”

Eliesen said the Ministry of Finance should have been involved in the decision to launch the program in 2016 and must share the blame for the losses.

BC Hydro CEO Chris O’Riley, appointed to the top job in 2017, and the corporation’s board are also responsible, Eliesen said, noting that the majority of directors are now NDP appointees, including board chairman Kevin Peterson.

The Ministry of Finance didn’t respond to Tyee queries, and BC Hydro wouldn’t answer questions about the hedging losses, citing the election campaign.

The Association of Major Power Customers, which represents large electrical consumers that account for 20 per cent of the province’s electrical demand, criticized BC Hydro’s debt management strategy.

“In an environment of lingering low-interest rates, ratepayers would benefit more from avoiding short-term hedging than they would from interest-rate certainty,” the association said.

In the last decade, BC Liberal and the NDP governments have used the Crown corporation as a political football, interfering in the process of setting rates, overpaying for electricity generated by private power producers, allowing irregular accounting, subsidizing oil and gas companies and overestimating future electrical demand.

As well, the Site C project megaproject is far over budget and facing significant geotechnical difficulties that will likely push costs even higher.

Despite a host of critics asking for a temporary halt to construction while an independent assessment of geotechnical risks takes place, BC Hydro opened diversion channels on the Peace River’s north bank on the weekend.

“The media and the public have to be more educated on how this big Crown agency operates,” said McCandless. “There needs to be more focus on costs and less political interference.”

*Story corrected on Oct. 8 at 10:16 a.m. to reflect the month when BC Hydro released its first-quarter report.  [Tyee]

Read more: Energy

  • Share:

Facts matter. Get The Tyee's in-depth journalism delivered to your inbox for free

Tyee Commenting Guidelines

Comments that violate guidelines risk being deleted, and violations may result in a temporary or permanent user ban. Maintain the spirit of good conversation to stay in the discussion.
*Please note The Tyee is not a forum for spreading misinformation about COVID-19, denying its existence or minimizing its risk to public health.

Do:

  • Be thoughtful about how your words may affect the communities you are addressing. Language matters
  • Challenge arguments, not commenters
  • Flag trolls and guideline violations
  • Treat all with respect and curiosity, learn from differences of opinion
  • Verify facts, debunk rumours, point out logical fallacies
  • Add context and background
  • Note typos and reporting blind spots
  • Stay on topic

Do not:

  • Use sexist, classist, racist, homophobic or transphobic language
  • Ridicule, misgender, bully, threaten, name call, troll or wish harm on others
  • Personally attack authors or contributors
  • Spread misinformation or perpetuate conspiracies
  • Libel, defame or publish falsehoods
  • Attempt to guess other commenters’ real-life identities
  • Post links without providing context

LATEST STORIES

The Barometer

Do You Think Naheed Nenshi Will Win the Alberta NDP Leadership Race?

Take this week's poll